Kaynarca Merkez
Kaynarca Central Station is common station for short and long lines. Peron levels of the lines are seperate, concourse level and entrance exist structurues are common. NATM tunnel works shall be carried out from one construction shaft. Total construction area is 14.265 m².
Station Work Progress
Excavation Support :%12,56
RC Works :%0
Architectural Works :%0
Traffic Diversions: Tevfik İleri Street has been narrowed as per UKOME decision dated 27.05.2021, no UTK2021/20-54.